DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 579 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live

Portfolio Breakdown · Province

579Awarded739Total
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn1681681681680390.1716,769.216,772.910610611,068.78,082.66263%4,049.91,572.919% of contract51.7%51.5%4534711
Tender Below 50Mn3583583583580305.3310,497.510,457.43003008,972.46,498.85884%3,509.52,506.039% of contract55.3%74.6%197127615
PIU247522274.043,493.93,493.93122,003.22,119.91243%——0.0%0.0%———3
Not Specified363600360.000.0209.30—0.00.0360%————————
Tender Total58656953154838769.5430,760.730,933.540941822,044.316,701.316872%7,559.44,079.024% of contract54.0%68.1%2421512329
Direct LabourDL Stage 0157575757082.202,471.62,469.557572,469.52,471.60100%1,885.81,984.980% of contract91.2%100.0%57———
DL Stage 0243434343045.181,357.21,358.543431,358.51,357.20100%910.81,059.578% of contract67.5%99.9%421——
DL Stage 0327272727030.91949.4952.22727952.2949.40100%478.1642.968% of contract63.0%94.6%2313—
DL Stage 0443434343060.062,349.71,766.943431,766.92,349.70100%558.5976.642% of contract23.3%80.1%35251
Direct Labour Total1701701701700218.357,127.96,547.01701706,547.07,127.90100%3,833.24,663.965% of contract63.6%94.1%157481
—All Provinces75673970171838987.8937,888.637,480.557958828,591.323,829.316878%11,392.68,742.837% of contract56.8%75.7%3991913130

Avg Physical Progress per EE Division

At-Risk Projects

218
Portfolio Timeline· 526 scheduled projects Toggle
2025-06-19 today2027-03-11

Showing first 80 of 526 projects.

Portfolio · Awarded Works

Awarded Projects

19 projects

19/19 (filtered)

Filter awarded works

19 matching projects2 active

ActiveDelayed onlyDelay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/18/25/139/NWP/KRGRR/RDA/18/25/139
Akkara Panaha Mansandiye Sita Walahamulla Dakwa Margaya
90%
28,112,995.7541,102,824.35Awarded
2RR/RDA/19/25/38/NWP/PUTRR/RDA/19/25/38
North Dummaladeniya Cross Road
90%
10,005,001.7811,621,041.20Awarded
3RR/RDA/19/25/39/NWP/PUTRR/RDA/19/25/39
Renovation of Khemananda Road
95%
19,114,271.4522,000,226.26Awarded
4RR/RDA/25/24/01/SBP/RTPRR/RDA/25/24/01
From Delgas Junction To Vilehena Road
90%
30,346,327.4143,303,726.54Awarded
5RR/RDA/25/24/03/SBP/RTPRR/RDA/25/24/03
From Thunaghahena To Temple Road
95%
20,065,425.8227,753,891.86Awarded
6RR/RDA/25/24/10/SBP/RTPRR/RDA/25/24/10
From Deniya kade Market to Henyaya Road Via Keenagahaella Road
95%
31,673,916.4550,516,461.34Awarded
7RR/RDA/25/25/03/SBP/KGLRR/RDA/25/25/03
From Kehelpannala Junction to Pahala Kabawita Road
95%
71,786,959.2096,478,103.45Awarded
8RR/RDA/25/25/15/SBP/KGLRR/RDA/25/25/15
Moraliya Gagaboda Road
90%
38,093,328.6248,285,852.39Awarded
9RR/RDA/25/25/38/SBP/KGLRR/RDA/25/25/38
Development of the road near the closed tea factory on Edurapola Watta main road
95%
22,209,331.1030,599,205.16Awarded
10RR/RDA/25/25/39/SBP/KGLRR/RDA/25/25/39
Development of Gatayamulla Jagatpura Pannala Rasnadeniya road
95%
31,491,651.4032,775,992.83Awarded
11RR/RDA/07/25/02/SP/GALRR/RDA/07/25/02
Delgahabedda-Kirimatiya Margaya
93%
26,404,581.1650,069,275.91Awarded
12RR/RDA/07/25/05/SP/GALRR/RDA/07/25/05
Atawalawatta Sri Rewatha Viduhala Idiripita Margaya
95%
25,809,376.9745,727,567.86Awarded
13RR/RDA/07/25/09/SP/GALRR/RDA/07/25/09
Panwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa Margaya
98%
28,039,359.8842,959,652.18Awarded
14RR/RDA/07/25/19/SP/GALRR/RDA/07/25/19
SuriEla Margaya
96%
14,387,747.0018,573,267.25Awarded
15RR/RDA/09/25/08/SP/HMBRR/RDA/09/25/08
Carpeting Pissubedda Medagamgoda road
98%
28,923,336.7546,881,232.95Awarded
16RR/RDA/15/25/10—
Concreting to Internal at MMV School
95%
33,890,314.6633,890,314.66Awarded
17RR/RDA/17/25/08—
Concreting of Play Ground Road Mahadiulwewa Stage II
90%
43,210,842.7543,210,842.75Awarded
18RR/RDA/08/25/05—
Koggalla bus stand to Sooriyawewa Road
95%
127,573,213.52127,573,213.52Awarded
19RR/RDA/09/25/07—
Carpeting Dabewelena Gravel Road
98%
54,766,473.9554,766,473.95Awarded
Showing 1–19 of 19
Per page:
Source: DRRRP • 739 projects • Data updated 2026-11-02 10:30 • 16:25:51