DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/19/25/34/NWP/PUT

Carpeting & Development of Bodhirajapura 4th Lane

PuttalamNorth Western ProvincePuttalamDivisional SecretariatSampath ConstructionContractorLKR 12,568,847.50Contract Sum91 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress100%
Time Elapsed100%
176 days behind schedule

Project Timeline

LOA
2026-01-29
Completed
Possession
–
Pending
Commencement
2026-02-12
Completed
Scheduled Completion
2026-05-12
Completed
Anticipated Completion Date
2026-05-13
Delayed