DRRRP Awarded Dl DL Stage 01

RR/RDA/25/24/15

D03 Road Near the Yaka Poll

RatnapuraSabaragamuwa ProvincePelmadullaDivisional Secretariat-ContractorLKR 52,683,572.48Contract Sum93 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-09-21
Completed
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionPelmadulla
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kalthota