DRRRP Awarded Tender Tender Below 50Mn

Road from Pinnawatta Junction to Mr. Sandaruwan's shop on the Hapitiya entrance road

GampahaWestern ProvinceNittambuwaDivisional SecretariatJeyanthan ConstructionContractorLKR 15,498,360.00Contract Sum0 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress0%
Time Elapsed0%
106 days behind schedule

Project Timeline

LOA
2026-04-08
Completed
Possession
–
Pending
Commencement
2026-04-21
Completed
Scheduled Completion
2026-07-21
Completed
Anticipated Completion Date
–
Delayed