DRRRP Awarded Dl DL Stage 01

RR/RDA/11/25/12

Renovation of Chemmantheevu 4th Cross Street.

MannarNorthern ProvinceMannarDivisional Secretariat-ContractorLKR 25,184,287.62Contract Sum93 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-09-21
Completed
Anticipated Completion Date
2025-10-31
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorthern Province
DistrictMannar
DS Division-
GN Division-
Electorate-
PD RegionNorthern Province
CE RegionVavuniya
EE DivisionMannar
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Nanattan