DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/16/25/10KM/01/AKK/AMP

The road from the bridge near Ridee ela Temple to Island Plot No. 197

AmparaEastern ProvinceDehiaattakandiyaDivisional SecretariatSawsiri ConstructionContractorLKR 24,113,338.37Contract Sum91 daysProject Duration
17%
Complete
Physical Progress17%
Planned Progress100%
Time Elapsed100%
162 days behind schedule

Project Timeline

LOA
2026-02-23
Completed
Possession
–
Pending
Commencement
2026-02-25
Completed
Scheduled Completion
2026-05-26
Completed
Anticipated Completion Date
–
Delayed