DRRRP Awarded Dl DL Stage 02
Elkaduwa pare sita Japan para sanwardanaya kirima
KandyCentral ProvinceKundasaleDivisional Secretariat-ContractorLKR 48,931,555.87Contract Sum93 daysProject Duration
Commencement
2025-07-30
Completed
Scheduled Completion
2025-10-30
Completed
Anticipated Completion Date
2026-02-15
Completed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
DS Division-
GN Division-
Electorate-
PD RegionCentral Province
CE RegionKandy
EE DivisionKundasale
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Pathadumbara
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryDirect Labour
Implementation MethodDL Stage 02
Contract NameElkaduwa pare sita Japan para sanwardanaya kirima
Estimated Road Lengths1.50 km
Number of Roads1
Scope Summary-
Proposed ScopeAsphalt Overlaying
Project RemarkWork started on direct labour basis on 30/07/2025
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.RR/RDA/04/25/37
Tender StatusAwarded
Contract Amount48,931,555.87
Engineer Estimate Amount (LKR)48,931,555.87
Duration (Days)93
Estimate & Sanction Direct Labour
Estimate ReceivedReceived
Estimate Submitted2025-08-12
Estimate SanctionedSanctioned
Estimate Return Date—
Sanctioned Date2025-08-12
Sanctioned Length1.50 km
Sanctioned Amount48,931,555.87
Estimated StatusEstimated
Allocation MonitoringOther All
Implementation (Direct Labour)
DS Division (DL Sheet)Pathadumbara
Proposal Letter Date2025-06-17
Direct Cost (PS Estimate)—
Surface Completed1.50 km
Cumulative Expenditure to 20256,306,240.72
Cumulative Expenditure 202622,737,955.66
Outstanding (Ministry)—
Current Statusasphalt 1500m
Initial PhotosUploaded
Final Photos-
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2025-10-30
Anticipated Completion Date
2026-02-15
Duration Elapsed462 / 93 days
Schedule Status-370 days remaining
Anticipated Completion Date2026-02-15
Project CompletedYes
Completed Date—
Mobilization
Planned vs Actual
Physical Progress100% vs 100%
Financial Progress0% vs 100%
Progress MonitorCompleted
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Final expenditure
as at 2026-11-04 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2025-10-30
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 370 Days in Delay
Overall Progress
Overall
Planned: 100%Ahead by 0%
Financial Actual: 0.00 Mn / Planned 48.93 MnBehind 48.93 Mn
Critical Issues-
Kandy - Kundasale
Elkaduwa pare sita Japan para sanwardanaya kirima
Project Name:
Project #580 - Contract No. RR/RDA/04/25/37
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 12:55
Contract No. RR/RDA/04/25/37
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 100%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Elkaduwa pare sita Japan para sanwardanaya kirima
Project Name:
Project #580 - Contract No. RR/RDA/04/25/37
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 12:55
Contract No. RR/RDA/04/25/37
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-25
Snapshot value100%
Current progress100%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.