DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/06/25/42/CP/NE

AC Overlaying from Polpitiya Junction to 04th Mile Post (CH 3+700 – 8+700 km)

Nuwara EliyaCentral ProvinceNorwoodDivisional SecretariatUKS Lanka Engineering Pvt Ltd.ContractorLKR 220,116,957.84Contract Sum273 daysProject Duration
50%
Complete
Physical Progress50%
Planned Progress100%
Time Elapsed100%
74 days behind schedule

Project Timeline

LOA
2025-11-07
Completed
Possession
–
Pending
Commencement
2025-11-24
Completed
Scheduled Completion
2026-08-22
Completed
Anticipated Completion Date
2026-08-22
Delayed