DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/18/25/07/NWP/KRG

Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda

KurunegalaNorth Western ProvinceMahoDivisional SecretariatJayasinghe Constructions (Pvt) Ltd.ContractorLKR 59,247,280.29Contract Sum182 daysProject Duration
75%
Complete
Physical Progress75%
Planned Progress100%
Time Elapsed100%
176 days behind schedule

Project Timeline

LOA
2025-11-25
Completed
Possession
–
Pending
Commencement
2025-12-09
Completed
Scheduled Completion
2026-05-12
Completed
Anticipated Completion Date
2026-06-12
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionMaho
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/07
Tender ByProcurement Division