DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/18/25/11/NWP/KRG

Development of road from Dambulu Road to Havanathenna via Ehelagollaya

KurunegalaNorth Western ProvinceKurunegalaDivisional SecretariatShanho Enterprises Pvt Ltd.ContractorLKR 46,193,949.68Contract Sum119 daysProject Duration
65%
Complete
Physical Progress65%
Planned Progress100%
Time Elapsed100%
126 days behind schedule

Project Timeline

LOA
2026-02-18
Completed
Possession
–
Pending
Commencement
2026-03-04
Completed
Scheduled Completion
2026-07-01
Completed
Anticipated Completion Date
2026-08-01
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionKurunegala
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/11
Tender ByProcurement Division