DRRRP Awarded Dl DL Stage 02

RR/RDA/01/25/06

Development of Rambutan gahamula Suramya Mawatha using carpet in Magammana East Grama Niladhari Domain

ColomboWestern ProvinceAvissawellaDivisional Secretariat-ContractorLKR 16,341,118.27Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-08-09
Completed
Scheduled Completion
2025-11-07
Completed
Anticipated Completion Date
2025-11-15
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
DS Division-
GN Division-
Electorate-
PD RegionWestern Province
CE RegionColombo
EE DivisionAvissawella
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Homagama