DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/07/25/09/SP/GAL

Panwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa Margaya

GalleSouthern ProvinceHinidumaDivisional SecretariatDGSD ConstructionContractorLKR 28,039,359.88Contract Sum91 daysProject Duration
98%
Complete
Physical Progress98%
Planned Progress100%
Time Elapsed100%
323 days behind schedule

Project Timeline

LOA
2025-09-12
Completed
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2026-03-31
Delayed