RR/RDA/16/25/06

Improvement of Mosque Lane from beach Road to Jummah Mosque Lane (0+500)m

AmparaEastern ProvinceKalmunaiDivisional Secretariat-ContractorLKR 22,306,322.17Contract Sum64 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-08-23
Completed
Anticipated Completion Date
2025-09-30
Completed