DRRRP Awarded Dl DL Stage 01

RR/RDA/25/08/07

Ovitigamuwa Alahenpita margaya Sanwardanaya Kirima (RDA yatathe Idikirima Arambha kara atharamaga nawatha etha)

MataraSouthern ProvinceMataraDivisional Secretariat-ContractorLKR 29,034,089.99Contract Sum63 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-08-22
Completed
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionMatara
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kirinda Puhulwella