DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/10/25/18/NP/JFN

Atchuvely Industrial Road

JaffnaNorthern ProvinceJaffnaDivisional SecretariatSun Constructions (Pvt) Ltd.ContractorLKR 72,500,000.00Contract Sum91 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress100%
Time Elapsed100%
214 days behind schedule

Project Timeline

LOA
2025-12-12
Completed
Possession
–
Pending
Commencement
2026-01-03
Completed
Scheduled Completion
2026-04-04
Completed
Anticipated Completion Date
2026-05-31
Delayed