DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/SP/16/25/01/AKK/AMP

Rectification and Asphalt Surfacing on Ambahagawela -Namaloya Main Road

AmparaEastern ProvinceAmparaDivisional SecretariatSMA Careem Engineering Consultancy Services & Suppliers (Pvt) LtdContractorLKR 222,189,859.13Contract Sum182 daysProject Duration
34%
Complete
Physical Progress34%
Planned Progress100%
Time Elapsed100%
127 days behind schedule

Project Timeline

LOA
2025-12-18
Completed
Possession
–
Pending
Commencement
2025-12-31
Completed
Scheduled Completion
2026-06-30
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceEastern Province
DistrictAmpara
DS Division-
GN Division-
Electorate-
PD RegionEastern Province (Akkaraipattu)
CE RegionAmpara
EE DivisionAmpara
Authority Tier-
Authority Name-
Package No.RR/RDA/SP/16/25/01
Tender ByProcurement Division