DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/04/25/20/CP/KY

Carpeting road Ratemulla to Wendesiwaththa End

KandyCentral ProvinceKandyDivisional SecretariatWiscon (Pvt) LtdContractorLKR 36,995,817.10Contract Sum91 daysProject Duration
45%
Complete
Physical Progress45%
Planned Progress100%
Time Elapsed100%
272 days behind schedule

Project Timeline

LOA
2025-10-24
Completed
Possession
–
Pending
Commencement
2025-11-08
Completed
Scheduled Completion
2026-02-05
Completed
Anticipated Completion Date
2026-03-20
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
DS Division-
GN Division-
Electorate-
PD RegionCentral Province
CE RegionKandy
EE DivisionKandy
Authority Tier-
Authority Name-
Package No.RR/RDA/04/25/20
Tender ByProvincial Director