DRRRP Awarded Dl DL Stage 03

RR/RDA/08/25/05

Koggalla bus stand to Sooriyawewa Road

HambantotaSouthern ProvinceTangalleDivisional Secretariat-ContractorLKR 127,573,213.52Contract Sum92 daysProject Duration
95%
Complete
Physical Progress95%
Planned Progress100%
Time Elapsed100%
323 days behind schedule

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2026-02-28
Delayed