DRRRP Awarded Dl DL Stage 02
Concreting to Internal at MMV School
BatticaloaEastern ProvinceBatticaloaDivisional Secretariat-ContractorLKR 33,890,314.66Contract Sum99 daysProject Duration
Schedule Delay354 daysbehind schedule
354 days behind schedule
Commencement
2025-08-09
Completed
Scheduled Completion
2025-11-15
Completed
Anticipated Completion Date
2026-03-15
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceEastern Province
DistrictBatticaloa
DS Division-
GN Division-
Electorate-
PD RegionEastern Province
CE RegionBatticaloa
EE DivisionBatticaloa
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kattankudy
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryDirect Labour
Implementation MethodDL Stage 02
Contract NameConcreting to Internal at MMV School
Estimated Road Lengths0.70 km
Number of Roads1
Scope Summary-
Proposed ScopeConcrete Surfacing (G30)-150mm & Base(ABC)-100mm
Project Remark-
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.RR/RDA/15/25/10
Tender StatusAwarded
Contract Amount33,890,314.66
Engineer Estimate Amount (LKR)33,890,314.66
Duration (Days)99
Estimate & Sanction Direct Labour
Estimate ReceivedReceived
Estimate Submitted2025-07-23
Estimate SanctionedSanctioned
Estimate Return Date—
Sanctioned Date2025-07-29
Sanctioned Length0.70 km
Sanctioned Amount33,890,314.66
Estimated StatusEstimated
Allocation MonitoringBujet Proposal 3,000Mn
Implementation (Direct Labour)
DS Division (DL Sheet)Kattankudy
Proposal Letter Date2025-04-29
Direct Cost (PS Estimate)3,058,412.50
Surface Completed0.50 km
Cumulative Expenditure to 2025235,044.00
Cumulative Expenditure 202624,265,380.54
Outstanding (Ministry)—
Current StatusSurface Completed
Initial PhotosUploaded
Final Photos-
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2025-11-15
Anticipated Completion Date
2026-03-15
Duration Elapsed452 / 99 days
Schedule Status354 Days in Delay
Anticipated Completion Date2026-03-15
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress95% vs 100%
Financial Progress0% vs 100%
Progress MonitorDelay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Current expenditure
as at 2026-11-06 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2025-11-15
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 354 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 5%
Financial Actual: 0.00 Mn / Planned 33.89 MnBehind 33.89 Mn
Critical Issues-
Batticaloa - Batticaloa
Concreting to Internal at MMV School
Project Name:
Project #603 - Contract No. RR/RDA/15/25/10
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 12:55
Contract No. RR/RDA/15/25/10
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 95%
Weekly Planned (Physical %)
Presentage
Actual financial
Batticaloa - Batticaloa
Concreting to Internal at MMV School
Project Name:
Project #603 - Contract No. RR/RDA/15/25/10
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 12:55
Contract No. RR/RDA/15/25/10
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-25
Snapshot value95%
Current progress95%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.