DRRRP Awarded Dl DL Stage 04

RR/RDA/05/25/28

Adawala Udagama Road

MataleCentral ProvinceNalandaDivisional Secretariat-ContractorLKR 56,161,142.68Contract Sum154 daysProject Duration
75%
Complete
Physical Progress75%
Planned Progress100%
Time Elapsed100%
255 days behind schedule

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-22
Completed
Scheduled Completion
2026-02-22
Completed
Anticipated Completion Date
2026-04-20
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictMatale
DS Division-
GN Division-
Electorate-
PD RegionCentral Province
CE RegionMatale
EE DivisionNalanda
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Naula