DRRRP Awarded Tender Tender Above 50Mn
Padiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge
AmparaEastern ProvinceDehiaattakandiyaDivisional SecretariatVithu ConstructionContractorLKR 39,470,000.00Contract Sum91 daysProject Duration
Schedule Delay162 daysbehind schedule
162 days behind schedule
Commencement
2026-02-25
Completed
Scheduled Completion
2026-05-26
Completed
Anticipated Completion Date
–
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceEastern Province
DistrictAmpara
DS Division-
GN Division-
Electorate-
PD RegionEastern Province (Akkaraipattu)
CE RegionAmpara
EE DivisionDehiaattakandiya
Authority Tier-
Authority Name-
Package No.RR/RDA/STA II/16/25/03
Tender ByProcurement Division
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryTender
Implementation MethodTender Above 50Mn
Contract NamePadiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge
Estimated Road Lengths2.00 km
Number of Roads1
Scope Summary-
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.RR/RDA/STA II/16/25/03/AKK/AMP
Tender Batch No.-
Contractor NameVithu Construction
Consultant-
Tender StatusAwarded
LOA Date2026-02-06
Contract Amount39,470,000.00
Engineer Estimate Amount (LKR)60,426,139.14
Duration (Days)91
Tender Process Details Tender
Bid Notice Date2025-11-06
Tender Opening Date2025-12-05
BEC Evaluation Submitted2025-12-08
PC Decision Date2026-01-13
Intention to Award2026-01-21
Appeal Final Date2026-02-05
Possession of Site—
Completed Date—
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-05-26
Anticipated Completion Date
—
Duration Elapsed252 / 91 days
Schedule Status162 Days in Delay
Anticipated Completion Date—
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress65% vs 100%
Financial Progress0% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Current expenditure
as at 2026-11-06 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-05-26
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 162 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 35%
Financial Actual: 0.00 Mn / Planned 39.47 MnBehind 39.47 Mn
Critical Issues-
Ampara - Dehiaattakandiya
Padiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge
Project Name:
Project #79 - Contract No. RR/RDA/STA II/16/25/03/AKK/AMP
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 12:52
Contract No. RR/RDA/STA II/16/25/03/AKK/AMP
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 65%
Weekly Planned (Physical %)
Presentage
Actual financial
Ampara - Dehiaattakandiya
Padiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge
Project Name:
Project #79 - Contract No. RR/RDA/STA II/16/25/03/AKK/AMP
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 12:52
Contract No. RR/RDA/STA II/16/25/03/AKK/AMP
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-24
Snapshot value65%
Current progress65%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.