DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/25/25/03/SBP/KGL

From Kehelpannala Junction to Pahala Kabawita Road

KegalleSabaragamuwa ProvinceKegalleDivisional SecretariatSF ConstructionsContractorLKR 71,786,959.20Contract Sum90 daysProject Duration
95%
Complete
Physical Progress95%
Planned Progress100%
Time Elapsed100%
188 days behind schedule

Project Timeline

LOA
2025-12-22
Completed
Possession
–
Pending
Commencement
2026-01-01
Completed
Scheduled Completion
2026-04-30
Completed
Anticipated Completion Date
–
Delayed