DRRRP Awarded Dl DL Stage 01

RR/RDA/06/25/36

CWM Factory Road

Nuwara EliyaCentral ProvinceNuwara EliyaDivisional Secretariat-ContractorLKR 65,323,196.31Contract Sum93 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-09-21
Completed
Anticipated Completion Date
2025-11-10
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
DS Division-
GN Division-
Electorate-
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNuwara Eliya
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Thalawakale