DRRRP Awarded Dl DL Stage 01

RR/RDA/25/25/16

Ma dola Jansalu Mawatha Rathnapuara Colombo Road to Welangalla Maha ela Bridge

KegalleSabaragamuwa ProvinceRuwanwellaDivisional Secretariat-ContractorLKR 40,604,043.84Contract Sum97 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-09-25
Completed
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
DS Division-
GN Division-
Electorate-
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionRuwanwella
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Dehiowita