DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/07/25/17/SP/GAL

Dasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirima

GalleSouthern ProvinceGalleDivisional SecretariatP.H. Engineering Construction (Pvt) LtdContractorLKR 20,798,250.00Contract Sum91 daysProject Duration
47%
Complete
Physical Progress47%
Planned Progress100%
Time Elapsed100%
323 days behind schedule

Project Timeline

LOA
2025-09-11
Completed
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2026-01-30
Delayed

Swipe tabs to see all sections — tap to switch