RR/RDA/19/25/08/NWP/PUT
Carpeting of Velasia Main Road from Madurankuliya.
PuttalamNorth Western ProvincePuttalamDivisional SecretariatSri Ram ConstructionsContractorLKR 39,584,083.50Contract Sum119 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress100%
Time Elapsed100%
Schedule Delay214 daysbehind schedule
214 days behind schedule
Project Timeline
LOA
2025-11-20
CompletedPossession
–
PendingCommencement
2025-12-04
CompletedScheduled Completion
2026-04-04
CompletedAnticipated Completion Date
2026-05-04
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceNorth Western Province
DistrictPuttalam
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionChilaw
EE DivisionPuttalam
Authority Tier-
Authority Name-
Package No.RR/RDA/19/25/08
Tender ByProcurement Division
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount