DRRRP Awarded Dl DL Stage 04

RR/RDA/09/25/07

Carpeting Dabewelena Gravel Road

HambantotaSouthern ProvinceHambantotaDivisional Secretariat-ContractorLKR 54,766,473.95Contract Sum75 daysProject Duration
98%
Complete
Physical Progress98%
Planned Progress100%
Time Elapsed100%
308 days behind schedule

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-10-18
Completed
Scheduled Completion
2025-12-31
Completed
Anticipated Completion Date
2026-03-31
Delayed