DRRRP Awarded Dl DL Stage 01

RR/RDA/22/25/03

Hubaslinda Meda Margaya

BadullaUva ProvinceMahiyanganayaDivisional Secretariat-ContractorLKR 19,159,838.84Contract Sum97 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-06-21
Completed
Scheduled Completion
2025-09-25
Completed
Anticipated Completion Date
2025-10-31
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
DS Division-
GN Division-
Electorate-
PD RegionUva Province
CE RegionBadulla
EE DivisionMahiyanganaya
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Kandekatiya