DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/10/25/22/NP/JFN

Anaivilunthan Sudalai Road

JaffnaNorthern ProvincePoint PedroDivisional SecretariatYaso EngineeringContractorLKR 48,082,026.30Contract Sum91 daysProject Duration
65%
Complete
Physical Progress65%
Planned Progress100%
Time Elapsed100%
215 days behind schedule

Project Timeline

LOA
2025-11-07
Completed
Possession
–
Pending
Commencement
2026-01-02
Completed
Scheduled Completion
2026-04-03
Completed
Anticipated Completion Date
2026-06-03
Delayed