RR/RDA/10/25/25/NP/JFN
Palaiya Vaikal Veeethy
JaffnaNorthern ProvincePoint PedroDivisional SecretariatSun Constructions (Pvt) Ltd.ContractorLKR 54,450,000.00Contract Sum91 daysProject Duration
50%
Complete
Physical Progress50%
Planned Progress100%
Time Elapsed100%
Schedule Delay216 daysbehind schedule
216 days behind schedule
Project Timeline
LOA
2025-12-12
CompletedPossession
–
PendingCommencement
2026-01-01
CompletedScheduled Completion
2026-04-02
CompletedAnticipated Completion Date
2026-06-15
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceNorthern Province
DistrictJaffna
DS Division-
GN Division-
Electorate-
PD RegionNorthern Province
CE RegionJaffna
EE DivisionPoint Pedro
Authority Tier-
Authority Name-
Package No.RR/RDA/10/25/25
Tender ByProcurement Division
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
