DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 64 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:64 awarded · Southern Province
1,097.0M

1,097.0 Mn

Total Expenditure (incl. VAT)

50.1% of contract incl. VAT
62.5%

0

On Progress

40 / 64 awarded

54.7%

0

Completed

35 / 64 awarded

Portfolio Breakdown · Southern Province · Province

579Awarded739Total
Southern Province 64 awarded of 92 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn8888014.63683.9683.955421.7343.9363%61.250.915% of contract40.0%96.5%11—3
Tender Below 50Mn42424242030.321,171.31,171.73333964.5716.1979%592.6295.141% of contract86.7%90.2%15414—
PIU000000.000.00.00—0.00.000%————————
Not Specified161600160.000.00.00—0.00.0160%————————
Tender Total666650501644.951,855.31,855.738381,386.31,060.02858%653.8346.033% of contract80.6%91.0%165143
Direct LabourDL Stage 01777709.79318.4318.477318.4318.40100%314.5219.769% of contract85.7%100.0%7———
DL Stage 02666604.95148.9148.866148.8148.90100%148.9119.380% of contract100.0%100.0%6———
DL Stage 03333304.10156.0156.033156.0156.00100%156.0105.568% of contract100.0%98.3%21——
DL Stage 0410101010015.71506.0506.01010506.0506.00100%111.5306.561% of contract30.0%94.3%91——
Direct Labour Total26262626034.551,129.41,129.326261,129.31,129.40100%731.0751.066% of contract69.2%97.6%24200
—Southern Province929276761679.502,984.72,985.064642,515.62,189.52870%1,384.81,097.050% of contract76.0%93.7%407143

Avg Physical Progress per EE Division · Southern Province

At-Risk Projects · Southern Province

218
Portfolio Timeline· 58 scheduled projects · Southern Province Toggle
Portfolio · Awarded Works

Awarded Projects

16 projects

16/16 (filtered)

Filter awarded works

16 matching projects1 active

ActiveIn progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/07/25/02/SP/GALRR/RDA/07/25/02
Delgahabedda-Kirimatiya Margaya
93%
26,404,581.1650,069,275.91Awarded
2RR/RDA/07/25/05/SP/GALRR/RDA/07/25/05
Atawalawatta Sri Rewatha Viduhala Idiripita Margaya
95%
25,809,376.9745,727,567.86Awarded
3RR/RDA/07/25/09/SP/GALRR/RDA/07/25/09
Panwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa Margaya
98%
28,039,359.8842,959,652.18Awarded
4RR/RDA/07/25/17/SP/GALRR/RDA/07/25/17
Dasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirima
47%
20,798,250.0033,516,218.38Awarded
5RR/RDA/07/25/19/SP/GALRR/RDA/07/25/19
SuriEla Margaya
96%
14,387,747.0018,573,267.25Awarded
6RR/RDA/09/25/08/SP/HMBRR/RDA/09/25/08
Carpeting Pissubedda Medagamgoda road
98%
28,923,336.7546,881,232.95Awarded
7RR/RDA/09/25/09/SP/HMBRR/RDA/09/25/09
Development of the road in front of Godawela School to Ambussa Wela
60%
34,500,631.0047,452,621.54Awarded
8RR/RDA/09/25/11/SP/HMBRR/RDA/09/25/11
Development of Walasmulla Daluwakgoda School Road
20%
34,814,777.8048,463,720.72Awarded
9RR/RDA/09/25/13/SP/HMBRR/RDA/09/25/13
Development of the road from Puak Dandawa near Aligerappa house through Weerasijahagoda to Satinamaluwa Kapuduarawatta field.
60%
23,847,807.5030,673,898.39Awarded
10RR/RDA/08/25/05—
Koggalla bus stand to Sooriyawewa Road
95%
127,573,213.52127,573,213.52Awarded
11RR/RDA/07/25/01—
Keselgahahena Pradana Margaya (Kanu Paddathiya Bokku Samaga)
98%
76,680,545.1676,680,545.16Awarded
12RR/RDA/09/25/12—
Development of the road from Lunugamwehera Jadura Lake to Udaeva
92%
66,506,406.5766,506,406.57Awarded
13RR/RDA/09/25/06—
Raluwa main road
70%
17,377,865.9917,377,865.99Awarded
14RR/RDA/09/25/07—
Carpeting Dabewelena Gravel Road
98%
54,766,473.9554,766,473.95Awarded
15RR/RDA/09/25/14—
Development of road near Olu ara School
90%
101,801,692.33101,801,692.33Awarded
16RR/RDA/09/25/10—
Development of Valasmulla Pallekanda road from 3 km post to 5 km post
95%
84,525,263.2384,525,263.23Awarded
Showing 1–16 of 16
Per page:
Source: DRRRP • 92 projects • Data updated 2026-11-02 10:30 • 13:38:46