DRRRP Awarded Tender Tender Below 50Mn
Mulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru Margaya
GalleSouthern ProvinceGalleDivisional SecretariatStar Light ConstructionContractorLKR 13,805,759.00Contract Sum91 daysProject Duration
Commencement
2025-09-16
Completed
Scheduled Completion
2025-12-16
Completed
Anticipated Completion Date
2025-12-06
Completed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceSouthern Province
DistrictGalle
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionGalle
EE DivisionGalle
Authority Tier-
Authority Name-
Package No.RR/RDA/07/25/06
Tender ByProvincial Director
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryTender
Implementation MethodTender Below 50Mn
Contract NameMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru Margaya
Estimated Road Lengths0.52 km
Number of Roads1
Scope Summary-
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.RR/RDA/07/25/06/SP/GAL
Tender Batch No.-
Contractor NameStar Light Construction
Consultant-
Tender StatusAwarded
LOA Date2025-09-11
Contract Amount13,805,759.00
Engineer Estimate Amount (LKR)22,862,917.58
Duration (Days)91
Tender Process Details Tender
Bid Notice Date2025-08-11
Tender Opening Date2025-08-26
BEC Evaluation Submitted—
PC Decision Date—
Intention to Award—
Appeal Final Date—
Possession of Site—
Completed Date—
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2025-12-16
Anticipated Completion Date
2025-12-06
Duration Elapsed414 / 91 days
Schedule Status-323 days remaining
Anticipated Completion Date2025-12-06
Project CompletedYes
Completed Date—
Mobilization
Planned vs Actual
Physical Progress100% vs 100%
Financial Progress0% vs 100%
Progress MonitorCompleted
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Final expenditure
as at 2026-11-04 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2025-12-16
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 323 Days in Delay
Overall Progress
Overall
Planned: 100%Ahead by 0%
Financial Actual: 0.00 Mn / Planned 13.81 MnBehind 13.81 Mn
Critical Issues-
Galle - Galle
Mulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru Margaya
Project Name:
Project #441 - Contract No. RR/RDA/07/25/06/SP/GAL
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 13:35
Contract No. RR/RDA/07/25/06/SP/GAL
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 100%
Weekly Planned (Physical %)
Presentage
Actual financial
Galle - Galle
Mulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru Margaya
Project Name:
Project #441 - Contract No. RR/RDA/07/25/06/SP/GAL
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 13:35
Contract No. RR/RDA/07/25/06/SP/GAL
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-24
Snapshot value100%
Current progress100%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.