DRRRP Awarded Dl DL Stage 04

RR/RDA/07/25/01

Keselgahahena Pradana Margaya (Kanu Paddathiya Bokku Samaga)

GalleSouthern ProvinceGalleDivisional Secretariat-ContractorLKR 76,680,545.16Contract Sum0 daysProject Duration
98%
Complete
Physical Progress98%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-01-01
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
2026-03-31
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictGalle
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionGalle
EE DivisionGalle
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Akmeemana