DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/08/25/16/SP/MTR

Walgama Saddathissa Mawathe Primesity Niwasa Sankeernaye Prawesha Margaya Kapat yoda Sanwardanaya kirima

MataraSouthern ProvinceMataraDivisional SecretariatJagath constructionContractorLKR 7,623,062.15Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-10
Completed
Possession
–
Pending
Commencement
2025-10-24
Completed
Scheduled Completion
2026-01-23
Completed
Anticipated Completion Date
2025-01-07
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionMatara
Authority Tier-
Authority Name-
Package No.RR/RDA/08/25/16
Tender ByProvincial Director