RR/RDA/08/25/23

Epitakaduwa Krishantha Senarath Yapa Road (Eptakaduwa Budu medura to Mr. LG Jagath Yapa home)

MataraSouthern ProvinceMataraDivisional Secretariat-ContractorLKR 7,231,417.22Contract Sum62 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-16
Completed
Scheduled Completion
2025-11-16
Completed
Anticipated Completion Date
2025-10-31
Completed