DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/07/25/08/SP/GAL

Mahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya Kirima

GalleSouthern ProvinceHinidumaDivisional SecretariatEHL ConstructionsContractorLKR 27,637,049.00Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-03
Completed
Possession
–
Pending
Commencement
2025-10-17
Completed
Scheduled Completion
2026-01-16
Completed
Anticipated Completion Date
2026-02-09
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictGalle
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionGalle
EE DivisionHiniduma
Authority Tier-
Authority Name-
Package No.RR/RDA/07/25/08
Tender ByProvincial Director