DRRRP Awarded Dl DL Stage 04
Asphalting Meepawala henegewaththa road
GalleSouthern ProvinceGalleDivisional Secretariat-ContractorLKR 21,395,564.10Contract Sum101 daysProject Duration
Commencement
2025-11-19
Completed
Scheduled Completion
2026-02-27
Completed
Anticipated Completion Date
2026-02-28
Completed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceSouthern Province
DistrictGalle
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionGalle
EE DivisionGalle
Authority Tier-
Authority Name-
Package No.-
Tender ByDirect Labour
DS Division (DL Sheet)Bope Poddala
Not set›Not set›Not set
1 Civil Administration Province → District → DS → GN
2 RDA Engineering Chain PD Region → CE Region → EE Division
3 Local Government 29 MC · 36 UC · 276 PS
Authority Tier Scope
CategoryDirect Labour
Implementation MethodDL Stage 04
Contract NameAsphalting Meepawala henegewaththa road
Estimated Road Lengths0.53 km
Number of Roads1
Scope Summary-
Proposed Scope-
Project Remark-
Proposer
Name-
Position-
Address-
Mobile No—
Contractor & Award
Contract No.RR/RDA/07/25/22
Tender StatusAwarded
Contract Amount21,395,564.10
Engineer Estimate Amount (LKR)21,395,564.10
Duration (Days)101
Estimate & Sanction Direct Labour
Estimate ReceivedReceived
Estimate Submitted2025-12-03
Estimate SanctionedSanctioned
Estimate Return Date—
Sanctioned Date2025-12-10
Sanctioned Length0.53 km
Sanctioned Amount21,395,564.10
Estimated StatusEstimated
Allocation MonitoringOther All
Implementation (Direct Labour)
DS Division (DL Sheet)Bope Poddala
Proposal Letter Date2025-09-15
Direct Cost (PS Estimate)—
Surface Completed0.53 km
Cumulative Expenditure to 20254,899,304.40
Cumulative Expenditure 20264,124,500.80
Outstanding (Ministry)—
Current StatusAsphalt Completed
Initial Photos-
Final Photos-
No proposal linked to this project
Link an existing unlinked proposal to this project.
Proposal management requires full-edit permission.
Document Readiness
1 of 12 required documents received.
1 Received11 Pending
Contractual1/7
LOA IssuedYes
Agreement Signed—
Escrow Agreement—
Performance Bond—
Contract Doc. Received—
Insurance—
Advance Bond—
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-02-27
Anticipated Completion Date
2026-02-28
Duration Elapsed350 / 101 days
Schedule Status-250 days remaining
Anticipated Completion Date2026-02-28
Project CompletedYes
Completed Date—
Mobilization
Planned vs Actual
Physical Progress100% vs 100%
Financial Progress0% vs 100%
Progress MonitorCompleted
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
Expenditure Up To This Week
Cumulative expenditure in LKR Mn, inclusive of VAT only
IPC paid total Final expenditure
as at 2026-11-04 · incl. VAT
Weekly spend
Cumulative current − previous manual entry
Paid IPC total
Advances + IPCs paid · incl. VAT
Editing expenditure requires project edit permission.
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-02-27
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 250 Days in Delay
Overall Progress
Overall
Planned: 100%Ahead by 0%
Financial Actual: 0.00 Mn / Planned 21.40 MnBehind 21.40 Mn
Critical Issues-
Galle - Galle
Asphalting Meepawala henegewaththa road
Project Name:
Project #696 - Contract No. RR/RDA/07/25/22
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 13:35
Contract No. RR/RDA/07/25/22
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 100%
Weekly Planned (Physical %)
Presentage
Actual financial
Galle - Galle
Asphalting Meepawala henegewaththa road
Project Name:
Project #696 - Contract No. RR/RDA/07/25/22
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 13:35
Contract No. RR/RDA/07/25/22
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-10-25
Snapshot value100%
Current progress100%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.