DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/08/25/20/SP/MTR

Naymbala kendawala haraha wellethota margaye wedugoda sthanaye pethi bemma sahithawa Sanwardanaya kirima

MataraSouthern ProvinceMataraDivisional SecretariatRathnayake ConstructionContractorLKR 3,502,675.00Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-01
Completed
Possession
–
Pending
Commencement
2025-10-15
Completed
Scheduled Completion
2026-01-14
Completed
Anticipated Completion Date
2025-12-12
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionMatara
Authority Tier-
Authority Name-
Package No.RR/RDA/08/25/20
Tender ByProvincial Director