Asmagoda Galabadahena Margaya Sanwardanaya Palamu Adiyara

MataraSouthern ProvinceDeniyayaDivisional SecretariatInduwara ConstructionContractorLKR 11,168,036.00Contract Sum91 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-10-03
Completed
Possession
–
Pending
Commencement
2025-10-17
Completed
Scheduled Completion
2026-01-16
Completed
Anticipated Completion Date
2026-02-16
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSouthern Province
DistrictMatara
DS Division-
GN Division-
Electorate-
PD RegionSouthern Province
CE RegionMatara
EE DivisionDeniyaya
Authority Tier-
Authority Name-
Package No.RR/RDA/25/08/08
Tender ByProvincial Director