DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 171 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 12:46Live

Portfolio Breakdown · Province

171Awarded266Total
CategoryTotal PortfolioAwarded PortfolioPendingAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
TotalEstimate LKR MnAwardedAwarded Est LKR MnContract LKR Mn
Emergency15328,654.714426,716.524,785.9994%21,228.14,470.518% of contract85.3%38.9%10131192
DC - Roads3920,559.494,690.05,783.23023%14.4—0.4%5.2%3——6
DC - Slope5319,237.7103,073.43,258.54319%10.4—0.3%4.7%1——9
PD(CP) - Slope21478.08181.8177.71338%——0.0%0.0%———8
All Provinces26668,929.917134,661.834,005.39564%21,253.04,470.513% of contract71.9%33.3%141311925

Avg Physical Progress per EE Division

At-Risk Projects

92
Portfolio Timeline· 146 scheduled projects Toggle
2026-02-06 today2028-03-15

Showing first 80 of 146 projects.

Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)

Filter awarded works

0 matching projects2 active

ActiveIn progressCompleted
Showing 0–0 of 0
Per page:
Source: DRRRP • 266 projects • Data updated 2026-11-04 12:46 • 13:36:27