DRRRP Awarded Director

RDA/DC/DRP/CP/NE/NRW/02

REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000

Nuwara EliyaCentral ProvinceNorwoodDivisional SecretariatU.K.S Lanka Engineering (Pvt) LtdContractorLKR 374,859,845.10Contract Sum365 daysProject Duration
9%
Complete
Physical Progress9%
Planned Progress3.2%
Time Elapsed26.6%
On Track • 267 days left

Project Timeline

LOA
2026-07-16
Completed
Possession
2026-07-30
Completed
Commencement
2026-07-30
Completed
Scheduled Completion
2027-07-29
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNorwood
Package No.-
Tender By-
Scope
Contract NameREHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/CP/NE/NRW/02
Tender Batch No.-
Contractor NameU.K.S Lanka Engineering (Pvt) Ltd
ConsultantNorwood EE
Tender StatusAwarded
LOA Date2026-07-16
Contract Amount374,859,845.10
Engineer Estimate Amount (LKR)348,620,000.00
Duration (Days)365
CategoryDC - Roads