DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/RAT/25

Rehabilitation / Improvement and Asphalt Overlaying on Malwana Charney (6+020 - 11+000) & Construction of Gabion Wall at 2+510, 2+847

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatWijeratne ConstructionContractorLKR 242,356,869.50Contract Sum91 daysProject Duration
62%
Complete
Physical Progress62%
Planned Progress100%
Time Elapsed100%
120 days behind schedule

Project Timeline

LOA
2026-03-13
Completed
Possession
–
Pending
Commencement
2026-04-07
Completed
Scheduled Completion
2026-07-07
Completed
Anticipated Completion Date
2026-07-07
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Asphalt Overlaying on Malwana Charney (6+020 - 11+000) & Construction of Gabion Wall at 2+510, 2+847
Estimated Road Lengths- km
Number of Roads-
Scope SummaryConstruction of culverts, Edge Widening, Asphalt Overlaying & Construction of Gabion Walls
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/RAT/25
Tender Batch No.3
Contractor NameWijeratne Construction
Consultant-
Tender StatusAwarded
LOA Date2026-03-13
Contract Amount242,356,869.50
Engineer Estimate Amount (LKR)269,615,801.69
Duration (Days)91
CategoryEmergency