DRRRP Awarded Emergency

RDA/DRP/NWP/CHI/PUT/10

Rehabilitation / Improvement of Palavi - Kalpitiya Road (B349) and Etalai - Talawila (Jubily Mawatha) Road (B516) (0+900-1+200) Puttalam EE Division

PuttalamNorth Western ProvinceChilawDivisional SecretariatST MARY ConstructionContractorLKR 136,011,633.11Contract Sum182 daysProject Duration
14%
Complete
Physical Progress14%
Planned Progress95.3%
Time Elapsed85.2%
On Track • 27 days left

Project Timeline

LOA
2026-05-19
Completed
Possession
–
Pending
Commencement
2026-06-02
Completed
Scheduled Completion
2026-12-01
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictPuttalam
PD RegionNorth Western Province
CE RegionChilaw
EE DivisionChilaw
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Palavi - Kalpitiya Road (B349) and Etalai - Talawila (Jubily Mawatha) Road (B516) (0+900-1+200) Puttalam EE Division
Estimated Road Lengths- km
Number of Roads-
Scope SummaryConstruction of U drains
Contractor & Award
Contract No.RDA/DRP/NWP/CHI/PUT/10
Tender Batch No.10
Contractor NameST MARY Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount136,011,633.11
Engineer Estimate Amount (LKR)147,930,527.03
Duration (Days)182
CategoryEmergency