DRRRP Awarded Emergency

RDA/DRP/NWP/CHI/PUT/11

Rehabilitation / Improvement of Town Roads (Saltern Road, Marikkar Street, Poles Road, Rest House Road, Good Shed Road) and Puttalam Trincomalee Road (AA012) in Puttalam EE Division

PuttalamNorth Western ProvinceChilawDivisional SecretariatOmega Construction Company (Pvt) LtdContractorLKR 303,043,337.30Contract Sum182 daysProject Duration
35%
Complete
Physical Progress35%
Planned Progress95.3%
Time Elapsed85.2%
On Track • 27 days left

Project Timeline

LOA
2026-05-19
Completed
Possession
–
Pending
Commencement
2026-06-02
Completed
Scheduled Completion
2026-12-01
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictPuttalam
PD RegionNorth Western Province
CE RegionChilaw
EE DivisionChilaw
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Town Roads (Saltern Road, Marikkar Street, Poles Road, Rest House Road, Good Shed Road) and Puttalam Trincomalee Road (AA012) in Puttalam EE Division
Estimated Road Lengths- km
Number of Roads-
Scope SummarySlope protection by concreting, const. of drainage, culverts
Contractor & Award
Contract No.RDA/DRP/NWP/CHI/PUT/11
Tender Batch No.10
Contractor NameOmega Construction Company (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount303,043,337.30
Engineer Estimate Amount (LKR)290,051,718.48
Duration (Days)182
CategoryEmergency