BadullaUva ProvinceBadullaDivisional SecretariatSenarathna ContractorsContractorLKR 232,880,104.48Contract Sum182 daysProject Duration
73.5%
Complete
Physical Progress73.5%
Planned Progress100%
Time Elapsed100%
41 days behind schedule

Project Timeline

LOA
2026-03-13
Completed
Possession
–
Pending
Commencement
2026-03-27
Completed
Scheduled Completion
2026-09-24
Completed
Anticipated Completion Date
2026-09-24
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Bandarawela Welimada Road (0+000-6+000) (B-044)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining Structures
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/14
Tender Batch No.2
Contractor NameSenarathna Contractors
Consultant-
Tender StatusAwarded
LOA Date2026-03-13
Contract Amount232,880,104.48
Engineer Estimate Amount (LKR)274,546,113.13
Duration (Days)182