DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/22

REHABILITATION/IMPROVEMENT OF WELIMADA KIRKLEES ROAD ( From 0+000 to 17+250)

BadullaUva ProvinceBadullaDivisional SecretariatSuhada EnterprisesContractorLKR 246,717,227.79Contract Sum182 daysProject Duration
77%
Complete
Physical Progress77%
Planned Progress100%
Time Elapsed100%
41 days behind schedule

Project Timeline

LOA
2026-03-13
Completed
Possession
–
Pending
Commencement
2026-03-27
Completed
Scheduled Completion
2026-09-24
Completed
Anticipated Completion Date
2026-09-24
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameREHABILITATION/IMPROVEMENT OF WELIMADA KIRKLEES ROAD ( From 0+000 to 17+250)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining wall construction ,Gabion wall construction
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/22
Tender Batch No.3
Contractor NameSuhada Enterprises
Consultant-
Tender StatusAwarded
LOA Date2026-03-13
Contract Amount246,717,227.79
Engineer Estimate Amount (LKR)288,759,369.79
Duration (Days)182
CategoryEmergency