DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/07

Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-40+000)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAnura ConstructionContractorLKR 276,583,785.23Contract Sum91 daysProject Duration
15%
Complete
Physical Progress15%
Planned Progress100%
Time Elapsed100%
37 days behind schedule

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-06-29
Completed
Scheduled Completion
2026-09-28
Completed
Anticipated Completion Date
2026-09-28
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-40+000)
Estimated Road Lengths- km
Number of Roads-
Scope Summary3 km (Wearing+ Binder), Drain Construction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/07
Tender Batch No.8
Contractor NameAnura Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount276,583,785.23
Engineer Estimate Amount (LKR)299,052,002.52
Duration (Days)91
CategoryEmergency