RDA/DRP/SAB/RAT/EMB/07
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-40+000)
RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAnura ConstructionContractorLKR 276,583,785.23Contract Sum91 daysProject Duration
15%
Complete
Physical Progress15%
Planned Progress100%
Time Elapsed100%
Schedule Delay37 daysbehind schedule
37 days behind schedule
Project Timeline
LOA
2026-05-11
CompletedPossession
–
PendingCommencement
2026-06-29
CompletedScheduled Completion
2026-09-28
CompletedAnticipated Completion Date
2026-09-28
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-40+000)
Estimated Road Lengths- km
Number of Roads-
Scope Summary3 km (Wearing+ Binder), Drain Construction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/07
Tender Batch No.8
Contractor NameAnura Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount276,583,785.23
Engineer Estimate Amount (LKR)299,052,002.52
Duration (Days)91
CategoryEmergency
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
