Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Nuwara EliyaCentral ProvinceNuwara EliyaDivisional SecretariatSouthern Group Civil Construction (Pvt) LtdContractorLKR 266,045,892.19Contract Sum182 daysProject Duration
Schedule Delay5 daysbehind schedule
5 days behind schedule
Commencement
2026-05-02
Completed
Scheduled Completion
2026-10-30
Completed
Anticipated Completion Date
–
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNuwara Eliya
Package No.10
Tender By-
Scope
Contract NameRehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryRoad Marking Retaining wall Construction, Edge Wedining, Drain Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/69
Tender Batch No.4
Contractor NameSouthern Group Civil Construction (Pvt) Ltd
ConsultantNuwara Eliya EE
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount266,045,892.19
Engineer Estimate Amount (LKR)365,868,062.33
Duration (Days)182
CategoryEmergency
Document Readiness
7 of 12 required documents received.
7 Received5 Pending
Contractual5/7
LOA IssuedYes
Agreement SignedYes
Escrow AgreementYes
Performance BondYes
Contract Doc. Received—
Insurance—
Advance BondYes
Technical2/5
Source Approval RequestYes
Drawings SubmittedYes
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-10-30
Anticipated Completion Date
—
Duration Elapsed186 / 182 days
Schedule Status5 Days in Delay
Anticipated Completion Date—
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress56% vs 100%
Financial Progress31.3% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.9% of contract
IPC 1 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-07-14
LKR 47,743,979.60LKR 56,337,895.93CE Certified2026-07-26
LKR 47,095,176.49LKR 55,572,308.26PD Certified2026-08-01
LKR 47,095,300.00LKR 55,572,454.00DateAmount (excl. VAT)Amount (incl. VAT)
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 31.3% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified—
LKR 18,867,467.50LKR 22,263,611.65DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-07-10
LKR 9,456,799.81LKR 11,159,023.78CE Certified2026-07-17
LKR 10,979,182.13LKR 12,955,434.91PD Certified2026-08-29
LKR 10,979,182.13LKR 12,955,434.92DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-08-12
LKR 9,471,076.58LKR 11,175,870.36CE Certified2026-08-17
LKR 3,966,846.32LKR 4,680,878.66PD Certified2026-09-24
LKR 3,965,848.32LKR 4,679,701.02DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request—
LKR 2,465,743.35LKR 2,909,577.15CE Certified2026-09-25
LKR 2,462,015.40LKR 2,905,178.17PD Certified2026-10-19
LKR 2,472,911.18LKR 2,918,035.19DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 24Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 25Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-10-30
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 5 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 44%
Financial Actual: 83.38 Mn / Planned 266.05 MnBehind 182.67 Mn
Critical Issues-
Nuwara Eliya - Nuwara Eliya
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Project Name:
Project #69 - Contract No. RDA/DRP/CEN/NUE/NUE/69
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 12:58
Contract No. RDA/DRP/CEN/NUE/NUE/69
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 56%
Weekly Planned (Physical %)
Presentage
Actual financial
Nuwara Eliya - Nuwara Eliya
Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)
Project Name:
Project #69 - Contract No. RDA/DRP/CEN/NUE/NUE/69
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 12:58
Contract No. RDA/DRP/CEN/NUE/NUE/69
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 83.38 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Current pace+2% / week
Estimated completion2027-03-21
Weeks to 100%21.6
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot2026-10-30
Snapshot value56%
Current progress56%
Change+2%
Project Notes 0
No notes yet. Add the first note to start the conversation.