DRRRP Awarded Emergency

RDA/DRP/WP/COL/COL/07

Rehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400)

ColomboWestern ProvinceColomboDivisional SecretariatINK EngineeringContractorLKR 146,665,907.47Contract Sum91 daysProject Duration
12%
Complete
Physical Progress12%
Planned Progress100%
Time Elapsed100%
72 days behind schedule

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-05-25
Completed
Scheduled Completion
2026-08-24
Completed
Anticipated Completion Date
2026-08-24
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying, Culvert construction & Builtup darins
Contractor & Award
Contract No.RDA/DRP/WP/COL/COL/07
Tender Batch No.8
Contractor NameINK Engineering
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount146,665,907.47
Engineer Estimate Amount (LKR)140,313,104.48
Duration (Days)91
CategoryEmergency