DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/11

Rehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatD K S ConstructionContractorLKR 273,586,576.22Contract Sum91 daysProject Duration
42%
Complete
Physical Progress42%
Planned Progress100%
Time Elapsed100%
35 days behind schedule

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-07-01
Completed
Scheduled Completion
2026-09-30
Completed
Anticipated Completion Date
2026-12-30
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000)
Estimated Road Lengths- km
Number of Roads-
Scope Summary9 km Asphalt overlaying with 1 m widening. Culvert Nos 1 reconstruction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/11
Tender Batch No.8
Contractor NameD K S Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount273,586,576.22
Engineer Estimate Amount (LKR)328,908,478.03
Duration (Days)91
CategoryEmergency